BETHANY (Dhading) CHILDREN’s HOME BUILDING PROJECT:
In August 2009 we bought a piece of land measuring 2,738sq.ft. For our own new Children's Home building. Our present rented flat is too small for our growing youngsters and has limited outdoor space. The land was much sought-after as it already has road access (for building vehicles), water and electricity to the site. The extra land will provide us with a play area and a vegetable garden. Our new building will be two and a half storeys high with 12 rooms. After completion of the building we plan to increase the number of children from 10 to 20. We need to start building the end of 2009/beginning 2010 at the latest, with a timescale of one year.
PLEASE HELP this is an exciting project so we hope you will donate as generously as you can but any amount you can give will be greatly appreciated.
Full details of building costs are given below:-
Name of project: Faith Foundation’s (Dhading Children’s Home).
Location/Site: Nilkantha-1, Santa Bazzar, Dhading Nepal. Contract period: End of 09 to End 2010.
S. N. |
Description of items |
Quantity |
Rate |
Total amount NER |
Total amount £ |
| 01 |
Cement |
1200 bags |
800 |
9,60,000 |
8,350 |
| 02 |
Sand |
15 tips |
21,000 |
3,15,000 |
2,750 |
| 03 |
Brick |
30,000 pieces |
15 |
4,50,000 |
3,950 |
| 04 |
Rubble stone |
25 tips |
4,000 |
1,00,000 |
900 |
| 05 |
Iron rods |
7,000 kg |
110 |
7,70,000 |
6,700 |
| 06 |
Complete furnishings |
|
|
6,00,000 |
5,220 |
| 07 |
Plumbing, water supply n sanitation |
|
|
5,50,000 |
4,800 |
| 08 |
Complete electric work |
|
|
3,00,000 |
2,600 |
| 09 |
Labouring skilled/unskilled |
|
|
6,50,000 |
5,650 |
| 10 |
Finishing |
|
|
6,08,000 |
5,300 |
| 11 |
Price increase @ 10% |
|
|
5,30,300 |
4,600 |
Total cost |
58, 38,603 |
50,820 |
|